Discharge of Conditions

Project: Discharge of Conditions | Location: Knowsley Industrial Park, Kirkby | Date: April 2020

Project Overview

Planning Permission had been granted in April 2017 for the upgrading of the existing waste treatment plant, plus additional bulk liquid storage tanks in the form of two new tank farms along with a new hydrogeneration plant and distillation plant that included a thermal oxidiser unit. The investment was worth £16.5m and secured the future of the plant being the only facility of its kind in the UK.

Approach

The client approached MPD to discharge the pre-commencement planning conditions attached to the planning approval, so they could make a practical start on site before the expiry of the existing planning permission so they could avoid having to reapply again.

We met with the client and ran through the conditions which needed to be discharged and then agreed these with Knowsley Council. Due to time constraints we were really up against it in terms of the details we needed to supply to discharge the conditions and this was compounded by not having a main contractor appointed to the project.

Having a good relationship with Knowsley Council officers we were able to get the conditions we could discharge dealt with in a timely manner. In relation to the drainage and site waste management plan conditions, we renegotiated these with the Local Planning Authority, which resulted in these conditions being amended to allow Future Industrial Services to make a practical start on site without being in breach of the conditions.

Conclusion

The client was able to make a practical start on site to keep the planning permission alive. The development represented a £16.5m investment in the site and being the only facility of its kind in the country it was vital to the future of the site to be able to make a start on site prior to the expiry of the planning permission.